Variables
Description
What is this formula?
Number of Haul Trucks Required estimates the number of haul trucks needed to achieve a target mine production rate.
It is one of the most common fleet sizing calculations in mine planning and equipment selection. The formula compares the required production with the production capacity of a single truck.
The result is often rounded up to the next whole truck because partial trucks cannot be deployed.
When to use it
Use this formula when:
- Designing mine haulage fleets.
- Estimating equipment requirements.
- Planning production targets.
- Evaluating truck fleet expansion.
- Comparing haulage alternatives.
Example
A mine must transport 4500 t/h of material. Each haul truck can transport 300 t/h.
Data:
Pr = 4500 t/h
Pt = 300 t/h
Formula:
N = Pr / Pt
Substitution:
N = 4500 / 300
Result:
N = 15
The operation requires 15 haul trucks to achieve the target production rate.
Applications
- Open-pit mining
- Underground mining
- Fleet sizing
- Production planning
- Equipment selection
- Mine scheduling
Note
This formula provides the theoretical minimum fleet size. Actual operations generally require additional trucks to account for maintenance downtime, operator breaks, traffic delays, weather conditions, road maintenance, and operational variability. Fleet sizing studies commonly apply availability and utilization factors to obtain the final number of trucks required.